Assistant Project Manager - Project quality control

0 years

0.0 Lacs P.A.

Hyderabad, Telangana, India

Posted:6 days ago| Platform: Linkedin logo

Apply Now

Skills Required

inspectionmanagementlibrarytestreportsdesignreportcoordinationqcbimdrawingtrackingcommissioningmaintenance

Work Mode

On-site

Job Type

Full Time

Job Description

Pre-construction Review and provide comments on the submitted GC’s Quality Control Plan. Verify inspection requirements are complete and identify additional opportunities of improvement as appropriate. Verify initial setup of Procore has the minimum: Creation and continuous management of Distribution Lists. Creation and continuous management of: Document Library Drawings Submittals Specifications Requests for Information (RFI) Test Reports Verify MEP clash detection and deconfliction within the design has taken place and issues resolved. Construction: Monitor GC’s construction activities and log activities in a weekly report that outlines the following: Discrepancies/observations found Change orders that were initialized due to quality Progress and inspection photos. Project overall cleanliness and housekeeping efforts Verify all work in place confirms to contract documents. Verify and input discrepancies found in to Procore and note in the weekly report. Attend Owner, Architect, and Contractor (OAC) weekly meetings. One QA representative must physically attend meetings, other representatives may attend physically or virtually. Status of Submittals. Status of outstanding issues/observations. Status of Requests for Information (RFI). In coordination with the GC’s QC Plan, attend and provide input to the following meetings: QA/QC kick off meeting Regularly scheduled MEP meetings Regularly scheduled QA/QC meetings Regularly scheduled BIM and As-Built drawing meetings Continuous review and tracking of submittal register. Conduct review on RFI associated with Change Orders. Provide a report on the quantity and attributes of RFIs when the project crosses L3. Confirm all RFI's indicate if costs were identified when RFI was submitted by GC. Outline all RFIs which had a cost impact and identify if the RFI could have been mitigated before the project award. Verify all critical equipment deliveries are damage free and match approved submittals. Ensure all findings are recorded Verify As-Built drawings have been created, regularly updated, Evaluate that the final installed product has been installed, checked inspected, and signed off, in order to proceed into commissioning Review and provide comments on the GC’s ā€œClose Out Binderā€ which includes: Critical equipment Preventative Maintenance Manuals and Schedules Warranty information for Equipment, materials, and building envelope Verify corrective actions for construction deficiencies are completed and recorded. Show more Show less

JLL
JLL

Real Estate

Chicago Illinois +

10001 Employees

726 Jobs

    Key People

  • Christian Ulbrich

    CEO
  • Greg O'Brien

    Global Chief Operating Officer

RecommendedJobs for You